PG Process Ltd. – United Kingdom

2010

Preparation of technical task and documentation for implementation of new CIP management system in BOOTS – UK. The scope of the work includes onsite investigation and preparation of technical task for the building of new CIP management system with all the necessary requirements and functionalities included.

SIEMENS EOOD

2010

Engineering for development and implementation of automation system for data collecting and integrated presenting of the information in substation ”Suvorovo” of wind park “Suvorovo”. The scope of the work includes configuration and programming of SICAM PAS server, configuration and programming of PAS CC operator station, start-up, commissioning and putting into exploitation.

PG Process Ltd. – United Kingdom

2011

Development and implementation of management software for the new CIP management system in BOOTS – UK. The scope of the work includes software development for the programmable controllers and the SCADA system, onsite start-up, commissioning and putting into exploitation.

NEOCHIM AD

2011
Chemical and pharmaceutical industry

Turn-key development and implementation of management and control system on site “Automation of the management system of the steam installation of NEOCHIM AD”. The scope of the work includes equipment delivery, construction and mounting work, electrical and control boards assembly, building of optic communication network, programming of controllers, programming of network switches, programming od SCADA system, start-up, commissioning and putting into exploitation, personnel training, executive documentation preparing.

NEOCHIM AD

2011
Chemical and pharmaceutical industry

Turn-key development and implementation of management and control system of the transport belts in buildings 402, 404 and 405 of workshop area 640 in NEOCHIM AD. The scope of the work includes equipment delivery, construction and mounting work, electrical and control boards assembly, building of optic communication network, programming of controllers, programming of network switches, programming od SCADA system, start-up, commissioning and putting into exploitation, personnel training, executive documentation preparing.

PROVADSOL AD

2011

Development and implementation of management control system of pressure pump 6kV. The scope of the work includes equipment delivery, electrical and control board assembly, programming of SIMATIC S7-300 controller, programming of operator panels, management software development, start-up, commissioning and putting into exploitation.

“Carlsberg Bulgaria” AD

2011
Food industry

Delivery, engineering and implementation of technical equipment and BRAUMAT 6.0 software for management and control of the brewing process in Shumen Brewery. The scope of the work includes equipment and system software delivery, revision of the controller software for work with the new version of the BRAUMAT software, revision of the SCADA software for work with the new version of the BRAUMAT software, installation, commissioning and adjustment of operator stations and network equipment, replacement of INTERBUS communication with PROFIBUS, start-up, commissioning and putting into exploitation.

“Balkanpharma Troyan” AD

2011
Chemical and pharmaceutical industry

Delivery of equipment and engineering for development and implementation of management and control system of three material pumps and one mixing vessel in workshop “РЦ „Унгвенти”” on the basis of programmable controller SIMATIC ET200S IM151-8 PN/DP, production of SIEMENS AG – Germany. The scope of the work includes equipment delivery, onsite mounting and wiring of the equipment, programming of the controller, programming of the operator panels, start-up, commissioning and putting into exploitation, personnel training.

TPP “ROUSSE”

2011
Chemical and pharmaceutical industry

Reconstruction and certification according to module “F” of automatic conveyor belt scale weighers 08A and 08B in Coal Transport Center of TPP “Rousse – East”. The scope of the work includes project development, equipment delivery, onsite mounting and wiring of the equipment, programming of the belt scale weighers, calibration of the weighers, start-up, commissioning and putting into exploitation, personnel training, participation in control tests for certification of the weighers according to module “F” together with authorized certification laboratory.

TPP “ROUSSE”

2011
Chemical and pharmaceutical industry

Development, implementation and certification according to module “F” of automatic conveyor belt scale weigher of coal belt transporter 01A in TPP “Rousse – East”. The scope of the work includes project development, equipment delivery, onsite mounting and wiring of the equipment, programming of the belt scale weigher, calibration of the weigher, start-up, commissioning and putting into exploitation, personnel training, participation in control tests for certification of the weigher according to module “F” together with authorized certification laboratory.